Turkish construction glossary: 81 terms from drawings to payments

This glossary explains 81 Turkish terms used every day on site and in construction offices, in six groups: drawings and rooms, quantities and estimates, payments and deductions, contracts and tenders, scheduling, and site and permits. Each entry gives the Turkish term, a close English equivalent and a short explanation.

Line drawing of a theodolite on a tripod beside an open floor plan

How to use this glossary

The Santix interface is in Turkish, and so is most paperwork on a Turkish site. The English equivalents here are the closest common terms, not exact legal translations. For official definitions on public works, see the General Specification for Works (Yapım İşleri Genel Şartnamesi) and the relevant laws. Rates and periods are general rules; confirm them with your accountant or lawyer.

Drawings, sheets and rooms

TurkishEnglishMeaning
AntetTitle blockBox on the sheet with project, sheet number and title, scale, date and signatures.
AplikasyonSetting outMarking grid lines, columns or corners on the ground.
As-builtAs-built drawingDrawing of what was actually built.
Bilgi talebiRequest for information (RFI)A written question to the designer that the drawing does not answer.
Brüt alanGross areaArea including walls; used for zoning, not for finishes.
DWG / DXFCAD file formatsDWG is AutoCAD's native format, DXF the exchange format.
Islak hacimWet areaBathroom, WC, kitchen or balcony needing waterproofing.
Kat yüksekliğiStorey heightFloor level to the next floor level.
KotLevelHeight relative to a datum, such as ±0.00 or +2.70.
LayoutPaper spacePrint page in a CAD file, usually one per sheet.
MahalRoom, spaceEvery coded space in a project.
Mahal koduRoom codeUnique code such as Z-01.
Mahal künyesiRoom data sheetOne record with a room's areas, heights, finishes, doors and notes. Room data sheets
Mahal listesiRoom and finish scheduleProject annex listing every room with its finishes. Guide
Model alanıModel spaceWhere drawing happens at full size; many Turkish offices draw all sheets side by side here.
Net alanNet areaArea between finished wall faces; floor and ceiling quantities come from it.
PaftaDrawing sheetOne sheet of a set, such as A-101 ground floor plan.
RevizyonRevisionA changed sheet reissued as a new version. Guide
Temiz yükseklikClear heightFinished floor to finished (or suspended) ceiling.
Uygulama projesiConstruction drawingsThe full set detailed enough to build from.

Quantities and estimates

TurkishEnglishMeaning
AtaşmanMeasurement recordSite measurement and sketch of work that will be hidden, signed jointly on public works.
Birim fiyatUnit ratePrice per m², m³ or piece.
Birim fiyat tarifiRate descriptionText defining what a rate covers and how it is measured.
İhzaratMaterials on siteDelivered but not yet built in.
İmalatWork doneWork carried out on site.
KeşifEstimateQuantities and approximate cost taken from the drawings.
Keşif özetiBill of quantities summaryItems with code, quantity, rate and amount.
MetrajQuantity take-offMeasuring work in the unit of its rate. Guide
MtülLinear metreUnit for skirting, sills and similar.
PozItem codeNumber of a rate item, used in rates and payments.
Yaklaşık maliyetPre-tender estimateThe client's estimated total before tender.
Yeşil defterQuantity summary bookPublic-works ledger of quantities per item: total, previous and this period.

Payments and deductions

TurkishEnglishMeaning
AvansAdvance paymentPaid up front against a guarantee.
Avans mahsubuAdvance recoveryDeducting the advance from each payment at a set rate.
Damga vergisiStamp dutyTax on contracts and payment certificates; 9.48 ‰ on contracts.
Fiyat farkıPrice adjustmentExtra payment from indexing contract prices.
Geçici hakedişInterim paymentPeriodic, not final.
Gecikme cezasıDelay penaltyUsually a daily per mille of the price.
HakedişProgress payment certificateValue of work done in a period and the amount payable. Guide
KDV tevkifatıVAT withholdingBuyer declares part of the VAT; 4/10 on construction.
Kesin hakedişFinal accountLast payment on final quantities.
Kümülatif hesapCumulative billingTotal to date minus previous payments.
Nefaset kesintisiQuality deductionPrice reduction for acceptable but sub-standard work.
StopajWithholding tax5 % on multi-year construction work.
Teminat kesintisiRetentionShare of each payment held as security; 5–10 % common.

Contracts and tenders

TurkishEnglishMeaning
Alt yüklenici (taşeron)SubcontractorTakes part of the work from the main contractor.
Asgari işçilikMinimum labour cost reviewSocial security check of declared labour against a minimum ratio.
Birim fiyatlı sözleşmeRemeasurement contractPaid on measured quantity × rate.
Eser sözleşmesiContract for workCode of Obligations contract type for building works.
Götürü bedelLump sumFixed price for a defined scope.
İbranameReleaseWritten statement that no further claims remain.
İhaleTenderCollecting and evaluating bids.
İş artışıVariation (increase)More work at contract rates within a limit.
İş sahibi (işveren)Client, employerThe party paying for the work.
Mücbir sebepForce majeureEvent outside both parties' control.
SGK ilişiksizlik belgesiSocial security clearanceProof of no social security debt for a job.
Teklif mukayese tablosuBid comparison tableBids side by side, line by line. Guide
Teminat mektubuBank guarantee, bondBank's undertaking to pay if the contractor defaults.
Yıllara sari işMulti-year workSpans calendar years; withholding tax applies.

How these become contract clauses: see the subcontract checklist.

Scheduling

TurkishEnglishMeaning
Ara terminInterim milestone dateDate by which part of the work must be complete.
BağımlılıkDependency (FS, SS, FF, SF)Sequence link between two tasks.
BaselineBaselineThe approved original programme.
BollukFloatDays a task can slip without moving the finish date.
Gantt şemasıGantt chartTasks as bars on a time axis.
İş paketiWork package, tradeGroup of work given to one subcontractor or team.
İş programıProgramme, scheduleDurations, sequence and dates of the work.
Kilometre taşıMilestoneZero-duration key event.
Kritik yolCritical pathZero-float chain that sets the finish date. Guide

Site and permits

TurkishEnglishMeaning
All-risk sigortasıContractor's all-risk insuranceCovers damage to the works during construction.
Geçici kabulProvisional acceptanceFirst acceptance at completion; the warranty starts.
Günlük raporDaily site reportWork, crews, weather and events of the day. Guide
İSGOccupational health and safetySubject of Law no. 6331.
İskanOccupancy permitPermit to use the finished building.
Kesin kabulFinal acceptanceAt the end of the warranty; remaining retention is usually released.
OSGBOccupational health service providerSupplies safety specialists and workplace doctors.
Periyodik kontrolPeriodic inspectionStatutory inspection of cranes, scaffolds, electrics. Guide
Risk değerlendirmesiRisk assessmentSafety document listing hazards and controls.
Şantiye şefiSite managerTechnical person responsible for the works on site. Role
Yapı denetimBuilding inspection firmLicensed firm supervising design and works under Law no. 4708.
Yapı ruhsatıBuilding permitMunicipal permit to start construction.
Yer teslimiSite handoverRecorded handover of the site; time often runs from it.

Where these terms appear in Santix

Santix uses these Turkish terms as they are used on site: sheets, title blocks, revisions and rooms in Paftalar; room data, net area and finishes in Mahaller; dependencies, critical path and milestones in İş programı; bids and estimates in Satın alma; lump sum, unit price, retention and penalties in Sözleşmeler; hakediş and every deduction in Bütçe; permits, policies, bonds and inspection reports in Evrak. Santix does not produce the official documents themselves, such as the yeşil defter or public tender files. See all features.

Frequently asked questions

What is the difference between metraj and keşif?

Metraj is measuring quantities. Keşif multiplies those quantities by unit rates to give an estimated cost; the keşif özeti is its summary table.

What does hakediş mean?

A hakediş is the periodic progress payment certificate: the value of work done to date, minus previous payments and deductions, giving the amount payable.