Which documents must be on a Turkish construction site?
Site paperwork falls into four groups: zoning and permit (the building permit, or yapı ruhsatı, with its approved drawings, the contract with the yapı denetim firm, the licensed third-party inspector every project must appoint, and the site manager's undertaking), social security (the SGK workplace file), occupational health and safety (OHS) records, and commercial documents (insurance, bank guarantees, subcontracts, municipal permits). Zoning Law 3194, art. 29, requires the permit and its attachments to be kept on site, and the Work Equipment Regulation, art. 7, requires inspection reports to be available whenever an inspector asks.
Start by knowing your hazard class. In the current Workplace Hazard Classes list, residential and non-residential building construction (NACE 41.00.01 and 41.00.02), concrete work and scaffold erection are all "very hazardous" (çok tehlikeli). The periods below use that class.
Document and validity table
| Document | Period | Legal basis | Owner |
|---|---|---|---|
| Building permit | Start within 2 years; finish within 5 years including the start period | Law 3194 art. 29 | Project manager |
| OHS risk assessment | At least every 2 years (4 hazardous, 6 low hazard); immediately after changes, accidents or near misses | Risk Assessment Reg. art. 12 | OHS specialist |
| Emergency plan | At least every 2 years; drill at least yearly | Emergency Reg. arts. 13, 14 | OHS specialist |
| Worker OHS training | At least yearly, minimum 16 hours | Training Reg. 2026 arts. 13, 14 | OHS specialist |
| Periodic health examination | At least yearly | Workplace Physician Reg. art. 9 | Workplace physician |
| Building scaffold inspection | At least every 6 months, plus after erection, raising or alteration | Work Equipment Reg. art. 7, Annex III | Site manager |
| Tower and mobile cranes | At least yearly; capacity load test at least every 3 years and after major repairs | Annex III 2.2.1 | Site manager |
| Hoists, mobile work platforms | At least yearly | Annex III Table 2 | Site manager |
| Electrical installation, earthing, lightning protection | At least yearly | Annex III Table 3 | Site manager |
| Compressor air receivers, pressure vessels | At least yearly | Annex III Table 1 | Site manager |
| Excavators, backhoe loaders, dump trucks | At least yearly | Annex III Table 6 | Plant manager |
| Contractor's all-risk policy, bank guarantees | Expiry on the document | Contract | Project manager, accounts |
| Excavation, haulage and dumping permits | Expiry on the permit | Municipality | Site manager |
Equipment periods are maximums that apply when the relevant standard sets nothing shorter. Since the December 2025 amendment, an inspection contract must be signed on the İSG-KATİP system at least 1 day before the inspection, and the report must carry the inspector's EKİPNET registration number. Reports without these can fail an audit.
How often is the risk assessment renewed?
At least every 2 years on very hazardous workplaces, but the same article requires a full or partial update whenever the workplace, technology, equipment or methods change, or after an accident or near miss. A construction site changes every month, so in practice you update the relevant section each time a new phase starts or heavy plant arrives. The emergency plan follows the same 2, 4 and 6-year logic, with a drill at least once a year.
When must scaffold and crane reports be renewed?
Building scaffolds: at least every 6 months, and again after first erection and every time the scaffold is raised or altered. A facade scaffold that climbs floor by floor needs a new report at each lift. Cranes: at least yearly, with a load test at each inspection and a structural capacity test at least every 3 years and after major repairs. Fixed equipment is re-inspected after every relocation.
How should reminders and ownership work?
- List every item. Each scaffold, crane, generator and compressor is its own line.
- Take expiry dates from the document, not from memory, and add post-erection checks.
- Give each document one owner: permits to the project manager, OHS to the OHS specialist, equipment to the site manager, guarantees and SGK to accounts.
- Remind at 30, 14, 7 and 1 days: time to book the inspector, confirm the date, check it happened, and a final warning.
- Archive, do not delete, the old certificate when the new one arrives.
- Review monthly everything expired or due within 30 days.
What is needed for the occupancy permit?
The occupancy permit (yapı kullanma izni, or iskân) is requested from the authority that issued the building permit, which must decide within 30 days (Law 3194, art. 30). Lists differ by municipality; commonly requested items include the inspection firm's completion documents, an SGK clearance letter, the energy performance certificate and lift registration where there is a lift. Start the file early, since clearance letters can take weeks. Contract dates such as guarantee and insurance expiry come from your subcontracts; see contract templates.
Checklist
- Permit and approved drawings on site, current versions.
- Permit date + 2 years and + 5 years in the calendar.
- Risk assessment and emergency plan match the current phase.
- Every worker's training and health check within the last year.
- Every scaffold inspected within 6 months and after its last lift.
- Crane, electrical, earthing, compressor and plant reports within a year, with EKİPNET numbers.
- Every document has an owner and 30/14/7/1-day reminders.
How does this work in Santix?
The Documents section of Santix holds permits, the inspection contract, risk assessment, emergency plan, training and health records, all-risk policy, bank guarantees, inspection reports, lift and occupancy documents per project. You scan a document with the camera; type, number and expiry date are read and suggested for you to check. Notifications go out 30, 14, 7 and 1 day before expiry, and expired documents show in red. Santix does not decide legal periods for you; you confirm the expiry date from the document. See document tracking and the revision guide for permit-level drawing changes. The app interface is in Turkish.
Sources
- Zoning Law No. 3194, arts. 29, 30
- Regulation on Health and Safety in the Use of Work Equipment, art. 7 and Annex III
- OHS Risk Assessment Regulation, art. 12
- Regulation on Emergencies at Workplaces, arts. 13, 14
- Workplace Physician Regulation, art. 9
- Worker OHS Training Regulation, Official Gazette 2 April 2026, No. 33212
Checked on 13 November 2026. All-risk, guarantee and municipal permit periods depend on the contract or municipality, so no general period is given.
Frequently asked questions
How often must a construction risk assessment be renewed in Türkiye?
At least every 2 years, because building construction is very hazardous, and immediately after changes to the work, new equipment, an accident or a near miss.
How often are scaffolds inspected?
Building scaffolds at least every 6 months unless the standard requires more often, plus after first erection and every time they are raised or altered.
How long is a Turkish building permit valid?
Work must start within 2 years of the permit date and finish within 5 years including that start period; otherwise the permit lapses and a new one is needed.